Source: TMR
The Department of Transport and Main Roads (TMR) is continuing geotechnical, contamination, pavement and Public Utility Plant (PUP) investigations adjacent and along the Gateway Motorway, between Bracken Ridge and the Pine River and surrounding ancillary roads from July to December 2026
July till December 2026.
This work continues to inform detailed design underway for the project.
Main construction is expected to start from late 2026, subject to environmental approvals.
Utility identification and locating works including vacuum excavation, as required.
Geotechnical and contamination investigation including boreholes and digging test pits for samples in several locations.
Testing existing pavement conditions and structural assessments.

For more information
For up-to-date project information please visit Gateway Motorway, Bracken Ridge to Pine River upgrade | Department of Transport and Main Roads
Or contact the team on 1800 607 755 (during business hours) or email the team at gmbhu@tmr.qld.gov.au.